Solar plant with Zero Investment
Go Solar on Your Factory Roof with Zero Upfront Investment under the BOOT (Build–Own–Operate–Transfer) model. Just pay for the generated electricity at a fixed tariff for fixed tenure. MUCH LOWER THAN YOUR DISCOM RATE.
ADITYA TYAGI
5/8/20263 min read


Yes, it is possible to install a solar power plant on your factory rooftop with zero upfront investment under the BOOT (Build–Own–Operate–Transfer) model.
What is Zero upfront solar model
A model in which a solar developer installs and operates a solar power plant on customer's rooftop and bills monthly for the electricity generated by installed solar power plant, at a pre-agreed tariff per unit (kWh). This tariff can be equal to, lower than, or in some cases slightly higher than the current DISCOM rate, depending on the commercial arrangement. Customer pays tariff for a fixed contract period (PPA tenure). At the end of this tenure, the plant is transferred to customer and from that point onwards customer enjoy near-free electricity for the remaining life of the plant.
How Zero upfront solar model works
Example: Assume the following
Current grid electricity tariff: ₹8.50/kWh
Sanctioned load: 100 kVA
Average monthly electricity bill: ₹1,20,000
Model 1: Long-Term PPA (Long PPA)
In long term Model, the developer:
Installs the solar power plant at zero upfront cost to customer.
Customer signs a long-term Power Purchase Agreement (PPA), typically for 10 or 15 or 20 years at a fixed tariff that is lower than the current DISCOM rate.
During the PPA period:
Customer pay only for the solar energy generated at the agreed tariff.
The developer is responsible for plant performance, operation, and maintenance.
At the end of the PPA term (for example, after 15 years):
The plant is transferred to customer, often at₹ 1/-
Customer continue to enjoy nearly FREE ELECTRICITY from the plant for the remaining technical life (up to ~25–30 years) at minimal operating cost.
In long term PPA
Upfront cost to customer Zero
PPA tariff rate below DISCOM rate
PPA tenure 15 to 20 Years
Depreciation benefits Taken by developer
Generation Risk In developer's scope till the end of PPA (NO generation, No payment)
Customer Pays for Only for generated electricity
Model 2: Short-Term PPA (Short PPA)
Short-Term Model is slightly different:
The developer installs the solar power plant at zero basic cost, but GST is paid by customer at the time of commissioning.
The plant is billed to customer on Day 1, making customer, the owner of the asset from the beginning.
Because customer is the owner, customer is eligible to claim accelerated depreciation benefits as per applicable tax laws.
In the developer’s books, the project is treated as being on loan, and customer repay this loan indirectly through the tariff, that customer pay for generated units:
Customer pay a per-unit tariff for 5–7 years or as per contract.
This tariff may be equal to, higher than, or sometimes slightly lower than your DISCOM rate, depending on the structure.
Example: Tariff of ₹8.50/kWh for 5 years.
After the short PPA period (for example, 5 years):
Customer effective repayment is over.
Customer start saving significantly on power costs & these savings continue for the remaining life of the plant (up to ~30 years).
In short term PPA
Upfront cost to customer GST payable (8.9%)
PPA tariff rate May be higher/ lower/ equal to existing DISCOME rates
PPA tenure 5 to 7 Years
Depreciation benefits Taken by customer
Generation Risk In developer's scope till the end of PPA (NO generation, No payment)
Customer Pays for For generated electricity & may be for maintenance, insurance charges
BOOT / RESCO vs CAPEX (Self-Investment)
Under CAPEX (self-investment), you invest 100% of the project cost and take full responsibility for performance and maintenance. Under BOOT/RESCO, you shift much of that responsibility and risk to the developer.
Advantages of BOOT/ RESCO
Upfront investment Zero or very low by customer
Maintenance In developer's scope
Generation Risk born by developer
Engineering Done by developer
Disadvantages of CAPEX
Upfront investment Born by customer 100%
Maintenance Customer's responsibility
Generation Risk born by customer
Engineering Done by customer or by hired consultant
Minimum Eligibility Criteria for BOOT / RESCO
To make a BOOT/RESCO project commercially viable, developers generally look for minimum consumption and infrastructure:
Electricity bill
BOOT: Minimum ₹50,000 per month
RESCO: Minimum ₹2,00,000 per month
Sanctioned load
BOOT: Minimum 50 kVA
RESCO: Minimum 200 kVA
Rooftop area
RCC or tin-shed roof, shadow-free
Approx. 80 sq. ft. per kW of solar capacity required
Land (if ground-mounted)
Own or leased land, with lease period at least equal to the PPA tenure
Documents Required for BOOT / RESCO Evaluation
For a developer or financier to evaluate and approve a BOOT/RESCO project, you will generally be asked for:
Electricity bills of the last 12 months
Google Maps location of the factory
ITR (Income Tax Returns) for the last 3 years
Balance sheets for the last 3 financial years
Computation statements for the last 3 years
PAN details
Credit rating of at least BBB+ (required for RESCO)
Minimum turnover of ₹4 crore (required for RESCO)
